						Customer: 
								Município de Loures
							
                            	Local: 
								Loures 								 - Portugal															
Year: 
								2013							
Work done: 
								Rehabilitation Works  							
Building area: 
								560 m2 							
Deadline: 
								3,3 months							
Intervention area: 
								Education 
							
							
The work consisted of the rehabilitation, conservation and extension of the building and remodeling of the patio. It was made a profound restructuring of the property, creating a new area on the 1st floor, extending the rear area of the building. The work was entirely carried out during the school holidays.
The planned intervention involved the following works:
- Earthmoving to remodel the public area - patio;
- Remodeling of the main entrance to the school;
- Remodeling of the patio through the creation of recreational areas;
- Remodeling of classrooms (including flooring works, execution of some walls with brick masonry, plasters and paintings);
- Demolition of part of the building;
- Overall construction of a new building including sanitation infrastructures, electricity, ITED, masonry, floors, plasters and coatings.
- New sanitary facilities, kitchen, cafeteria, storeroom, school library and two classrooms.